When You Assume
Andy Clark   (April 1, 2009)





The plan looks good on paper. Competent professionals are executing it. But unexpected delays and costs still crop up. It could be the one area of project management where your years of experience can actually hurt you: assumptions. So how do you weed them out of your plan? Here are some unassuming ideas.

It happened to me again last week in the initiation phase of an Archiving Implementation project. We completed a successful proof of concept and were moving ahead with the implementation, which required a refreshed database. I had asked the database administrators (DBAs) how long it would take to build the refresh and they answered “4 hours.” I assumed this was a full estimate of the time required for the refresh, based on my experience working with DBAs on similar activities. What I didn’t realize is that changes in storage technology had changed our refresh procedures and this was now a System Administrator operation as much as a DBA operation. Consequently the estimate did not include either the System Administrator work or the coordination work.
 
I hadn’t waited until the last minute to get started, so this false assumption didn’t cause a delay in the project’s critical path, but it did cost some of my time and caused work to be done on a quasi-emergency basis rather than as a planned activity.
 
Every time I turn around, I run into an assumption.



Please login/register to read the entire article.





Sponsored Announcements and Special Offers
Project Management Software That Breaks the Mold - Is your team is struggling under the weight of outdated schedules, multiple spreadsheets, and mountains of email? Get organized, get visibility, and save up to 3 hours a day with LiquidPlanner. Scheduling has never been easier with drag-n-drop prioritization that fits the way YOUR team works. Free for 30 days.

Resource Planning Summit, Sept. 19-21, 2010, La Jolla, CA - Resource Planning is HOT today! Opening Keynoter Mike Hanford, Research Director at Gartner, will describe why, and what firms must do about it. Nine industry speakers will describe the startling results they have achieved. If you have anything to do with resource management, register NOW!

ProjectWorld® & World Congress for Business Analysts® is the premier conference for advancing collaboration through practice. The high level content cannot be found at any other industry event because it stretches far beyond the fundamentals to provide leadership, strategy and enterprise wide information - exactly what you need to be more valuable to yourself and your organization.

Are you ready to gain the highest recognition for a BA and apply the best practices defined in the Business Analysis Body of Knowledge®? Let us help you prepare for Certified Business Analysis Professional® certification with our CBAP® Exam Prep Course. We also provide CBAP® Application Workshops (free webinars) to help you successfully get approved for the CBAP® application.

Are your Business Analysis Skills Current? Business analysis is not just about IT requirements anymore. Organizations are looking for a new breed of professionals to bridge the business and technology gap with value-centric solutions. Develop the fundamental skills and best practices you need to stay ahead of changes in your field with our business analysis training offerings.




@task
BAM! BA Newsletter
BAMentor
IIL
Keller Graduate School
LiquidPlanner
Management Concepts
Microsoft
PM War Stories
PPM Executive Newsletter
Resource Plan Summit '10
RMC Project Mgmt
Stanford University
Walden University

September 2010:

What are the main reasons that projects fall behind schedule?



Copyright © 2010 projects@work  All rights reserved.

Privacy Policy    Contact Us    User Agreement