To Be Accurate...
Curt Finch
(September 8, 2005)
|
|
By paying attention to the time spent in the requirements and specifications phases, and correlating estimates to timesheet data, you can more accurately predict and track overall project length. If more companies did, fewer undoable projects would ever start.
Have you ever worked in a place where 10 percent of 10 projects got done instead of 100 percent of one project? Ultimately, nothing is accomplished and everyone is totally stressed out. Inaccurate estimates cause over-commitment of time, yet not much gets done. Inaccurate estimates also cause bad decisions. “Inaccurate” usually means “too low.” When this happens, the return on investment (ROI) calculation shows the project as ‘worth it’ when it is not.
How can you stop wasting your company’s resources on projects that are not worth corporate time? Robert Grady’s book, Practical Software Metrics for Project Management and Process Improvement, gave us the answer more than a decade ago. In it, Grady provides a few insightful rules of thumb that are backed up by real numbers, such as: 6-8 percent of software project time is spent in the requirements and specifications phase. This is based on statistics from numerous software projects at Hewlett-Packard, so the percentage at your company may be different. The good news is that for projects of a particular flavor, you will find that the percentage usually doesn’t vary wildly, so you can use it to predict all project effort required for completion.
Let’s take an example group of projects in an imaginary IT shop in a large company, XYZ Corp. XYZ’s IT shop likes to write special applications on a regular basis (rather than be slaves to SAP or Oracle) and they’ve discovered the following:
- All software projects have the following phases:
- Requirements: What the internal client wishes XYZ would do
- Specifications: What XYZ is actually going to do.
- Design: How XYZ is going to do it.
- Coding: XYZ writes the application.
- Testing: XYZ tests that it works internally.
- Rollout: XYZ puts it into production.
- Debug: XYZ does the first 90 days of maintenance.
- After tracking time accurately on seven projects of this flavor, the CIO finds that 6 percent to 15 percent of all engineering hours are spent on phases ‘a’ and ‘b’ combined, with an average of 10 percent.
Now a new project comes up: the Wizbang Application Integration Project.
Please login/register to read the entire article.
Sponsored Announcements and Special Offers
|
Join us July 29th for a live 1-hour webinar: The Power of Virtual Collaboration in Project Management and learn how stakeholders and team members dispersed across the globe keep everyone informed, involved and on track. Hear Terrence Gargiulo, President of MAKINGSTORIES.net, share real-life stories of how companies use virtual collaboration technology to address these challenges and effectively manage projects.
2009 Resource Planning Summit, June 29-30, Chicago
Resource Planning is essential to product development where "time to market" and innovation are crucial. Hear testimonials from Medtronic, Motorola, Wyeth and IDEXX. Learn why you are not getting the juice out of your Resource Planning and earn PMI PDUs! CLICK HERE FOR MORE
On-campus Summer courses still available. Whether preparing for the PMP or needing PDUs to stay up to date, UC Berkeley provides top-notch instructors and valuable information you can use right away.
Free White Paper, Learn how a new approach to IT Governance speeds implementation. Click here to download.
The Stanford Advanced PM Certificate Program provides professionals with advanced tools and techniques to strategically execute projects, programs, and portfolios. Learn more about 2.0 in action.
|
|
|
|
|