6 Steps to a Better WBS
William Duncan   (April 10, 2008)




The work breakdown structure is supposed to be a fundamental tool for identifying project work to be budgeted, scheduled and staffed. But misunderstandings abound and it often fails to provide useful benefits. No wonder so many project managers swear at it, not by it. Here are six steps to creating a better WBS (no B.S.).

The first time I taught a class in project management was well before the days of PowerPoint and LCD projectors. In fact, my initial set of overhead slides was created by hand since color printers were more expensive than manual labor. As a result, I tried to keep the amount of text down to an absolute minimum. So on the slide that introduced the concept of a work breakdown structure, I used the acronym “WBS” without ever spelling the term out in full.
 
I was well aware of the potential for confusion, and I am pretty sure that I explained what the acronym stood for. But either I hadn’t, or I hadn’t done it very well, because not long after I began to discuss the WBS, a student at the back of the room raised a hand and asked, “I understand what the last two letters stand for, but what does the first one mean?” While I was still trying to digest that question, another student towards the front of the room called out “wholesale!”
 
Unfortunately, this perception is all too common.



Please login/register to read the entire article.





Sponsored Announcements and Special Offers
Join us July 29th for a live 1-hour webinar: The Power of Virtual Collaboration in Project Management and learn how stakeholders and team members dispersed across the globe keep everyone informed, involved and on track. Hear Terrence Gargiulo, President of MAKINGSTORIES.net, share real-life stories of how companies use virtual collaboration technology to address these challenges and effectively manage projects.

2009 Resource Planning Summit, June 29-30, Chicago
Resource Planning is essential to product development where "time to market" and innovation are crucial. Hear testimonials from Medtronic, Motorola, Wyeth and IDEXX. Learn why you are not getting the juice out of your Resource Planning and earn PMI PDUs! CLICK HERE FOR MORE

On-campus Summer courses still available. Whether preparing for the PMP or needing PDUs to stay up to date, UC Berkeley provides top-notch instructors and valuable information you can use right away.

Free White Paper, Learn how a new approach to IT Governance speeds implementation. Click here to download.

The Stanford Advanced PM Certificate Program provides professionals with advanced tools and techniques to strategically execute projects, programs, and portfolios. Learn more about 2.0 in action.




Citrix GoToMeeting
IAG Consulting
IBM
Innotas
Management Concepts
Microsoft
PM War Stories
PMI-CPM Conference
PMI Risk Management
RMC Project Mgmt
Stanford University
UC Berkeley Extension

VIEW NEW WHITE PAPERS

July 2009:

Four questions about project resources, collaboration and communication.



Copyright © 2009 projects@work  All rights reserved.

Privacy Policy    Contact Us    User Agreement