6 Steps to a Better WBS
William Duncan   (April 10, 2008)





The work breakdown structure is supposed to be a fundamental tool for identifying project work to be budgeted, scheduled and staffed. But misunderstandings abound and it often fails to provide useful benefits. No wonder so many project managers swear at it, not by it. Here are six steps to creating a better WBS (no B.S.).

The first time I taught a class in project management was well before the days of PowerPoint and LCD projectors. In fact, my initial set of overhead slides was created by hand since color printers were more expensive than manual labor. As a result, I tried to keep the amount of text down to an absolute minimum. So on the slide that introduced the concept of a work breakdown structure, I used the acronym “WBS” without ever spelling the term out in full.
 
I was well aware of the potential for confusion, and I am pretty sure that I explained what the acronym stood for. But either I hadn’t, or I hadn’t done it very well, because not long after I began to discuss the WBS, a student at the back of the room raised a hand and asked, “I understand what the last two letters stand for, but what does the first one mean?” While I was still trying to digest that question, another student towards the front of the room called out “wholesale!”
 
Unfortunately, this perception is all too common.



Please login/register to read the entire article.





Sponsored Announcements and Special Offers
Project Management Software That Breaks the Mold - Is your team is struggling under the weight of outdated schedules, multiple spreadsheets, and mountains of email? Get organized, get visibility, and save up to 3 hours a day with LiquidPlanner. Scheduling has never been easier with drag-n-drop prioritization that fits the way YOUR team works. Free for 30 days.

Resource Planning Summit, Sept. 19-21, 2010, La Jolla, CA - Resource Planning is HOT today! Opening Keynoter Mike Hanford, Research Director at Gartner, will describe why, and what firms must do about it. Nine industry speakers will describe the startling results they have achieved. If you have anything to do with resource management, register NOW!

ProjectWorld® & World Congress for Business Analysts® is the premier conference for advancing collaboration through practice. The high level content cannot be found at any other industry event because it stretches far beyond the fundamentals to provide leadership, strategy and enterprise wide information - exactly what you need to be more valuable to yourself and your organization.

Are you ready to gain the highest recognition for a BA and apply the best practices defined in the Business Analysis Body of Knowledge®? Let us help you prepare for Certified Business Analysis Professional® certification with our CBAP® Exam Prep Course. We also provide CBAP® Application Workshops (free webinars) to help you successfully get approved for the CBAP® application.

Are your Business Analysis Skills Current? Business analysis is not just about IT requirements anymore. Organizations are looking for a new breed of professionals to bridge the business and technology gap with value-centric solutions. Develop the fundamental skills and best practices you need to stay ahead of changes in your field with our business analysis training offerings.




@task
BAM! BA Newsletter
BAMentor
IIL
Keller Graduate School
LiquidPlanner
Management Concepts
Microsoft
PM War Stories
PPM Executive Newsletter
Resource Plan Summit '10
RMC Project Mgmt
Stanford University
Walden University

September 2010:

What are the main reasons that projects fall behind schedule?



Copyright © 2010 projects@work  All rights reserved.

Privacy Policy    Contact Us    User Agreement